PK – 12 Addition/Renovation.

The Akron School District PK-12 Addition project is a 50,400 SF addition located in Akron, CO. This project was designed to LEED® certified standards (targeted Silver). As Commissioning Authority the RD3 Team will fulfilled (in progress) the following commissioning requirements:

  • Design Peer Review of Mechanical, Electrical Lighting and BAS / Controls System
  • Develop Construction-Phase Cx Plan
  • Develop Cx Specifications
  • Submittal reviews
  • Incorporate Cx Activities into project schedule/maintain schedule
  • Cx Meetings
  • Write/Distribute Installation Verification Checklist (IVC) Forms
  • Develop Functional Performance Tests (FPT)
  • Coordinate/Witness/Perform Functional Performance Tests (FPT) of all mechanical/HVAC-R, lighting and plumbing equipment/systems
  • Maintain Master Issues Log
  • O&M Manual Review
  • Develop the Measurement & Verification (M&V) Plan to meet the additional LEED EA credits.
  • Compile a Commissioning Record (Final Cx Report)
  • Review Training Requirements/Materials
  • Post Completion 10 Month Warranty Testing